The Challenge
The customer needed to clear a site located in New England and was working on a remediation plan to deal with heavily-regulated PCB waste in soil. They needed an expert partner to help them navigate the tricky cleanup that didn’t cause delays in the project.
Better VISIBILITY
- Heritage brought in the experts who were already well-versed in the right regulatory codes and definitions, in this case 40 CFR 761.61.
- We reviewed the draft work plan and suggested some language changes.
- The proposed changes allowed the client to explore all their disposal options to deal with the contaminated soil.
Better SOLUTIONS
- Before the project started, Heritage suggested pre-excavation sampling and testing to get ahead of the approval process.
- A careful profiling exercise meant disposal approval well in advance of commencement.
- Free to perform the work, Heritage managed the project to completion without any disruptions.
Proven IMPACT
- The quick approvals and smooth project management that Heritage provided saved an estimated 15 to 20 working days, almost an entire calendar month, for the customer.
- 15,000 tons of PCB remediation waste was removed from the site without incident.
20
Working days saved on the job site
15,000
Tons of PCB waste soil removed